Booked Flats for Rs 1.16 Crore, Awaited Possession for Years: MahaRERA Orders Builder to Refund Money With Interest
Two homebuyers who booked flats in a Mumbai-based real estate project in 2013 for a combined Rs 1.16 crore waited years for possession after being promised homes by December 2014. After discovering that the project had lapsed, they approached MahaRERA. The regulator ruled in their favour and ordered the builder to refund the amounts paid along with interest.
Written by
Jyoti Mukherjee

Flats Booked in 2013, Possession Promised by 2014
Kishor Krishnan Kutty and Deepak Laxmidas Thakkar each booked a flat in a Mumbai-based housing project in 2013.
The two homebuyers collectively paid around Rs 1.16 crore for the properties. According to the case details, possession was promised by December 2014. However, the flats were not delivered as promised, leaving the buyers waiting for years.
What began as a home purchase eventually turned into a prolonged dispute between the buyers and the developer.
Buyers Later Found That the Project Had Lapsed
A major issue emerged when the homebuyers discovered that the real estate project had lapsed.
The buyers had expected the developer to complete construction and hand over possession within the promised timeline. Instead, the project remained incomplete and possession was not delivered.
The dispute eventually reached the Maharashtra Real Estate Regulatory Authority, commonly known as MahaRERA, which examined the buyers' complaints and the developer's position.
Why the Buyers Purchased Flats on Unconstructed Floors
The case also raises an important question for prospective homebuyers: should buyers book flats on floors that have not yet been constructed?
The case involved flats above the fifth floor even though construction on those portions had not been completed at the time of booking. This highlights the risks buyers can face when purchasing property at an early stage of construction.
While early bookings can sometimes offer lower prices or other benefits, buyers need to verify the project's approvals, registration status, construction progress and completion schedule before making substantial payments.
Builder's Response to the Delay
During the dispute, the developer's responses regarding the delay and refund were considered by MahaRERA.
The homebuyers argued that the prolonged delay had deprived them of possession of their homes and that they should not be left bearing the financial consequences of the developer's failure to deliver the project as promised.
The regulatory proceedings ultimately went in favour of the buyers.
What MahaRERA Observed
MahaRERA examined the circumstances surrounding the bookings, the promised possession timeline and the status of the project.
The regulator found grounds to provide relief to the homebuyers and directed the builder to return the money paid by them along with applicable interest.
The order provides an important example of how real estate regulators can offer a legal avenue to buyers facing prolonged project delays or other serious issues.
Homebuyers to Get Money Back With Interest
The key outcome of the case was that the two homebuyers won relief before MahaRERA.
The builder was ordered to refund the amounts invested by the buyers along with interest. The decision means the buyers can seek recovery rather than remaining indefinitely tied to a project that failed to provide possession within the promised period.
The case demonstrates the potential importance of approaching the real estate regulator when negotiations with a developer fail to resolve a prolonged possession dispute.
How Much Money Will Each Homebuyer Get?
The two buyers had collectively paid approximately Rs 1.16 crore for their respective flats. The final amount recoverable by each buyer will include the relevant refund and interest as directed under the MahaRERA order.
The interest component is particularly significant because the buyers had been deprived of both the property and the use of their money for an extended period.
Why Traceable Payments Matter When Buying a Home
The case also highlights the importance of maintaining a clear financial trail when purchasing property.
Homebuyers should ideally make payments through traceable banking channels and preserve booking forms, allotment letters, agreements, payment receipts, correspondence with the developer and other relevant documents.
Proper documentation can become extremely important if a dispute later reaches a regulatory authority or court.
What Homebuyers Should Check Before Booking a Flat
The case offers several lessons for property buyers.
Before booking a flat, buyers should check the project's RERA registration, approvals, construction status and expected completion date. They should also verify whether the developer has the necessary permissions for the specific phase and floor being sold.
Buyers should carefully examine the agreement for sale and understand clauses relating to possession, cancellation, delay compensation and refunds.
It is also important to keep copies of every payment record and communication with the developer.
MahaRERA and Homebuyer Protection
MahaRERA was established to regulate real estate projects in Maharashtra and protect the interests of homebuyers.
For buyers facing delayed possession, incomplete projects or disputes with developers, the regulatory framework can provide a mechanism for seeking relief.
The present case underscores why buyers should not ignore prolonged delays and should understand their legal and regulatory options.
Conclusion
The case of two Mumbai homebuyers who collectively paid Rs 1.16 crore for flats booked in 2013 highlights the risks associated with delayed and lapsed real estate projects. After waiting years beyond the promised December 2014 possession date, the buyers approached MahaRERA and secured an order directing the builder to refund their money with interest.
For prospective homebuyers, the case serves as a reminder to verify RERA registration, construction progress, approvals and payment documentation before committing substantial sums to a property project.
Keep reading
More in Business & Economy

Business & Economy
Ultraviolette Raises $85 Million; Bira 91 Revival Plan Takes Shape
Electric motorcycle maker Ultraviolette has raised $85 million in fresh funding led by Yali Capital and TDK Ventures, with Intel CEO Lip-Bu…

Business & Economy
Bessemer Raises $5.75 Billion in New Funds, Expands Growth Efforts
Bessemer Venture Partners has raised $5.75 billion in new capital as the venture capital firm expands its focus on growth-stage investments,…

Business & Economy
UPI for Mutual Funds: Benefits, Limits and Impact of New MDR Explained
UPI has become a convenient way to invest in mutual funds through one-time payments and SIP mandates. From October 15, 2026, a new Merchant…

Business & Economy
Best Gilt Mutual Funds to Invest in September 2026
Gilt mutual funds invest predominantly in government securities and carry relatively low credit risk, but they are highly sensitive to inter…

Business & Economy
Helios Mid Cap Among Top 5 Midcap Mutual Funds With Highest Mid and Smallcap Exposure in August 2026
Helios Mid Cap Fund recorded the highest combined exposure to mid-cap and small-cap stocks among the top five midcap mutual funds tracked by…

Business & Economy
Mutual Fund AUM-to-Bank Deposit Ratio Triples in a Decade to 31% in August
India's mutual fund industry has expanded significantly relative to bank deposits over the past decade. As of August 2026, mutual fund asset…
